A heat loss calculation for a building permit in Ontario is the room-by-room estimate of how much heat a house loses on a design winter day, and how much heat it gains in summer where cooling is installed. It sizes the furnace or heat pump and the ducts, and it forms part of the building permit drawings for a house.

Prepared by Elmid Design Inc. · Reviewed by Hamid Akbari, P.Eng.
The image at the top of this page is illustrative only. It is not a project drawing and shows no design values.
This guide is for homeowners, builders and designers preparing a permit for a new house, an addition, a secondary suite or a basement that changes the heated area. It explains what the calculation is, the Building Code rules behind it, who may prepare it and what the rest of the HVAC design package contains.
Elmid Design Inc. prepares the calculation and the HVAC design. A licensed HVAC contractor of your choice supplies and installs the equipment.
What is a heat loss calculation for a building permit?
It is a documented calculation of the heating load of each room and of the whole house at the outdoor design temperature for the location. Where air conditioning is installed, a heat gain calculation does the same for cooling. Together they show the examiner that the equipment and ducts are sized from the house as designed.
People also call it a heat loss and heat gain calculation, a load calculation, an HVAC load calculation or simply “the F280”, after the CSA standard it follows.
A rule of thumb per square foot, or the size of the old furnace, is not a heat loss calculation. Two houses of the same floor area can have very different loads because of their windows, insulation, airtightness, orientation and basement.
The calculation is room by room for a practical reason. The duct design needs the airflow each room should receive, and that airflow follows from each room’s share of the load. A whole-house number alone cannot size a branch duct or a register.
Which Ontario Building Code rules require a heat loss calculation?
For a house under Part 9 of the 2024 Ontario Building Code (O. Reg. 163/24), Article 9.33.5.1 bases heating capacity on the heating load calculated under Article 9.33.4.1, which names CSA F280 as good engineering practice. The Code’s referenced edition is CSA F280-12. Outdoor design temperatures come from Supplementary Standard SB-1.
The current Code is the 2024 Ontario Building Code, O. Reg. 163/24, which replaced the previous Code, O. Reg. 332/12. The articles below were checked in the Province’s 2024 Building Code Compendium, Part 9 (updated October 20, 2026, accessed November 18, 2026).
- Article 9.33.4.1 requires heating, ventilating and air-conditioning systems to be designed, constructed and installed to good engineering practice, such as the ASHRAE Handbooks and Standards and CSA F280, “Determining the required capacity of residential space heating and cooling appliances”. Outside winter design temperatures must conform to SB-1.
- Article 9.33.5.1 says the heating system capacity shall be based on the calculated heating load, and the cooling capacity on the calculated cooling load where cooling is installed. Oversizing and undersizing are determined in accordance with CSA F280.
- Article 9.33.3.1 sets the indoor design temperatures: not less than 22 °C in all living spaces, 18 °C in unfinished basements, 18 °C in common service rooms, ancillary spaces and exits in houses with a secondary suite, and 15 °C in heated crawl spaces.
- Article 9.33.3.2 takes the outdoor design conditions for the location from SB-1, using 2.5 percent design temperature criteria.
The edition matters. Table 1.3.1.2 of the Compendium’s Division B, Part 1 (updated October 20, 2026, accessed November 18, 2026) lists CSA F280-12 for Sentences 9.33.4.1.(1) and 9.33.5.1.(3). A calculation for an Ontario permit should name that edition unless the municipality accepts another basis.
Section 9.33 applies to heating and air-conditioning systems serving only one dwelling unit, and to radiant heating systems in houses with a secondary suite. Other systems follow Part 6. Part 6 asks for good engineering practice such as the ASHRAE Handbooks and the HRAI Digest, but its general requirements do not name CSA F280; the F280 sizing rule above is a Part 9 rule.
What goes into a room-by-room heat loss and heat gain calculation?
The calculation uses the house as drawn: the area and construction of every wall, window, door, ceiling, floor and basement wall in each room, the insulation values, the expected air leakage and ventilation, and the indoor and outdoor design temperatures. Heat gain adds solar gain through windows, occupants and internal gains.
Most inputs come straight from the architectural drawings, so the calculation is only as current as the set it was based on.
| Input | Where it comes from |
|---|---|
| Room areas, ceiling heights and wall lengths | Architectural floor plans and sections |
| Window and door sizes, types and orientation | Floor plans, elevations and the window schedule |
| Wall, roof, floor and foundation insulation | Wall sections and the energy-efficiency summary |
| Air leakage and mechanical ventilation | The energy-compliance path and the ventilation design |
| Indoor design temperatures | Article 9.33.3.1 of the Code |
| Outdoor design temperatures | Supplementary Standard SB-1 for the municipality |
How is the calculation used to size equipment and ducts?
The total heating load sets the minimum output the furnace, boiler or heat pump must deliver, and the cooling load sets the air-conditioner or heat pump cooling capacity. CSA F280 limits how far equipment may be oversized or undersized. The room loads then set the airflow, duct sizes and register locations on each floor.
In practice the design follows a short chain, and each link depends on the one before it:
- Loads: heating and cooling load for each room and for the house.
- Equipment: a unit whose rated capacity suits the calculated loads, with the efficiency the energy-compliance path requires.
- Airflow: the share of the system airflow each room needs.
- Ducts: trunk and branch sizes, supply registers and return grilles drawn on each floor plan.
Oversized equipment is a common outcome of guessing. A furnace much larger than the load cycles on and off more often, and an oversized air conditioner can cool a room before it removes enough humidity. Sizing from a calculation avoids both, and the Code ties the sizing limits to F280 rather than to preference.
Who may prepare a heat loss calculation for a permit in Ontario?
For a house, a designer registered with the Province in the “HVAC – House” category, which carries a Building Code Identification Number (BCIN), can prepare it, as can a professional engineer. Some owners designing for a house they own are exempt from the designer qualification. The municipality decides whether a submission is complete and acceptable.
Division C, Part 3 of the Code sets designer qualifications. In the Compendium’s Part 3 (updated September 14, 2026, accessed November 18, 2026):
- Table 3.5.2.1 defines the “HVAC – House” class as building systems to which Section 9.32 (ventilation) or 9.33 (heating and air-conditioning) applies that are appurtenant to a house.
- Article 3.2.5.1 requires a person who carries out design activities to be registered with the director in the relevant class, unless an exemption applies. One exemption covers design work on a house owned by that person.
- Article 3.2.4.1 requires a business offering design services to the public to be registered too, but exempts design work on a house that relates only to plumbing, to heating, ventilation and air-conditioning, or to ancillary buildings such as garages. The individual designer’s qualification under Article 3.2.5.1 still applies.
- Article 3.2.5.6 requires a registered designer to show their name, registration number, a statement that they reviewed and take responsibility for the design, and their signature on documents submitted to the chief building official.
Engineers are handled separately on municipal forms. The City of Toronto, for example, requires its Schedule 1 Designer Information form “for all designers, except Engineers and Architects”, and asks exempt owners to fill it in to state the reason for the exemption.
What does the HVAC design package for a house permit contain?
The heat loss calculation is one part of a package. A municipality typically also expects equipment details, duct design calculations, a mechanical ventilation design and a layout of the system on each floor. The City of Toronto’s list is a useful example, but each municipality publishes its own checklist and decides what is complete.
Toronto’s Related Mechanical (HVAC) Permit page (City of Toronto, modified July 14, 2026, accessed November 18, 2026) lists this required documentation:
- layout of the mechanical system at each floor level;
- type, location and size of equipment;
- heat loss and heat gain calculations;
- duct design calculations;
- mechanical ventilation calculations and design.
Elmid’s guide to HVAC design drawings covers each part of the package in more detail, including how equipment efficiencies tie into the energy-efficiency path under Supplementary Standard SB-12.
When does a project need a new heat loss calculation?
A new calculation is commonly needed for a new house, an addition, a secondary suite, or a basement finish that adds heated space or changes the duct system. It is also needed when the architectural drawings change in ways that affect the loads. Whether a permit is needed for your work is the municipality’s decision.
- New house: a full calculation for every room, matched to the energy-compliance path.
- Addition: loads for the new rooms and a check of whether the existing equipment and ducts can serve them.
- Secondary suite: loads for each unit. Article 9.33.1.1 says air duct systems serving one dwelling unit in a house with a secondary suite must not be directly interconnected with other parts of the house, which shapes the design.
- Changes to an existing system: under Article 9.33.1.1, repairs or component replacements that change the capacity or safety of an existing system and alter how it operates must conform to the Code.
What causes examiner comments on a heat loss calculation?
Comments usually come from gaps or mismatches, not from the arithmetic: a calculation based on an older drawing set, design temperatures that do not match the location, equipment that does not match the calculated load or the energy-compliance path, or missing designer information. A coordinated set leaves fewer questions, though the review outcome stays with the municipality.
Check these points before you submit:
- The window sizes and insulation values in the calculation match the current architectural set.
- The outdoor design temperature is the SB-1 value for the municipality where the house is built.
- The selected equipment capacity is consistent with the calculated heating and cooling loads.
- The equipment efficiency matches what the energy-compliance path assumes.
- Room loads, duct sizes and register locations agree across the calculation and the floor plans.
- The designer’s name, registration details and responsibility statement are complete, or the engineer is identified.
What should you send Elmid before the calculation starts?
Send the current architectural drawings, the energy-compliance path if one has been chosen, the property’s municipality, your equipment preferences and any examiner comments. With those, Elmid can confirm the scope and prepare a written proposal. Please email files after first contact, because our contact form does not take attachments.
- Architectural drawings: floor plans, elevations, sections and the window schedule, in PDF and, if available, CAD.
- Energy-compliance path: the SB-12 package or method your designer selected, if already decided.
- Equipment preferences: furnace, boiler or heat pump, fuel type, and whether cooling or a heat recovery ventilator is planned.
- Existing system information: for an addition or suite, the make and capacity of the current equipment and a sketch of the existing ducts.
- Municipal checklist or comments: the checklist you are working from, or the examiner’s letter if you have already applied.
Frequently asked questions
Is a heat loss calculation required for a building permit in Ontario?
For a house where heating is installed or changed, the Code bases heating capacity on a calculated heating load (Article 9.33.5.1), and municipalities commonly ask to see that calculation. Toronto, for example, lists heat loss and heat gain calculations as required documentation for a related HVAC permit. Check your municipality’s own checklist.
What is CSA F280?
CSA F280, “Determining the required capacity of residential space heating and cooling appliances”, is the Canadian standard for residential heating and cooling loads. The 2024 Ontario Building Code names it in Articles 9.33.4.1 and 9.33.5.1 and lists the F280-12 edition in Table 1.3.1.2. Oversizing and undersizing limits are determined under it.
Who can prepare a heat loss calculation for a house permit?
A designer registered in the “HVAC – House” category with a BCIN, or a professional engineer. Some owners designing for a house they own are exempt from the designer qualification. Registered designers must show their name, registration number, responsibility statement and signature on submitted documents. The municipality decides whether the submission is acceptable.
Does Elmid install the furnace or air conditioner?
No. Elmid Design Inc. is an engineering consultant, not an HVAC contractor. We prepare the heat loss and heat gain calculation and the HVAC design within an agreed scope. Supply, installation and servicing are carried out by a licensed HVAC contractor that you engage directly.
How much does a heat loss calculation cost?
Costs depend on the project: the size of the house, whether cooling is included, and whether duct and ventilation design and other permit drawings are part of the scope. Send your drawings and the municipality to request a proposal; Elmid confirms the scope in writing before work starts.
Areas we serve
Elmid Design Inc. prepares heat loss calculations, residential HVAC design and building permit drawings for projects in Toronto and the Greater Toronto Area, including York, Peel, Halton and Durham regions. We also work in other Ontario municipalities, depending on project scope and availability. Contact us to discuss your project.
Related articles
- HVAC design drawings for a building permit in Ontario
- HVAC permit Toronto guide
- Building permit drawings in Ontario
Sources
- Ontario, 2024 Building Code Compendium, Division B, Part 9 — Housing and Small Buildings (Articles 9.33.1.1, 9.33.3.1, 9.33.3.2, 9.33.4.1, 9.33.5.1), updated October 20, 2026, accessed November 18, 2026.
- Ontario, 2024 Building Code Compendium, Division B, Part 1 — General (Table 1.3.1.2: CSA F280-12), updated October 20, 2026, accessed November 18, 2026.
- Ontario, 2024 Building Code Compendium, Division C, Part 3 — Qualifications (Articles 3.2.4.1, 3.2.5.1, 3.2.5.6; Table 3.5.2.1), updated September 14, 2026, accessed November 18, 2026.
- City of Toronto, Related Mechanical (HVAC) Permit, modified July 14, 2026, accessed November 18, 2026.
This article is general information, not advice for a specific property. Requirements vary by municipality and change over time; confirm current requirements with your municipality before you apply.