Prepared by Elmid Design Inc. · Reviewed by Hamid Akbari, P.Eng.
An Oakville lot grading and drainage plan is a sealed drawing of the existing and proposed ground elevations, drainage routes and servicing for your lot. At Elmid Design Inc., a Professional Engineer prepares it from your topographic survey and architectural drawings, and visits the finished site for the final lot grading certificate where the Town requires one. The Town can require a plan with a site alteration permit for pools, landscaping, retaining walls, rebuilds and additions, and with building permits for new structures, additions and rebuilds that change the footprint.
This guide covers the Town of Oakville’s own rules. For the service across Ontario, see our site grading and drainage plan service.
Key takeaways
- Oakville’s grading plan rules for houses are set out in the Town’s Grading and Servicing Plan Guide for Residential Infill Developments (August 2023) and its Development Engineering Procedures and Guidelines manual (Version 2.0, September 2023).
- The plan is prepared, sealed, signed and dated by a Professional Engineer or an Ontario Land Surveyor.
- It must show existing and proposed elevations, drainage arrows and slopes, swales, downspouts, sump pump discharge, house siting elevations, servicing and erosion and sediment control.
- After the work, a P.Eng. or OLS signs a lot grading certificate based on a site inspection within the previous 30 days.
When do you need a grading plan in Oakville?
You need one when your project requires a Development Engineering (DENG) permit for work on your lot, or a building permit for a new structure, an addition or a rebuild that changes the footprint. Section 3 of the Town’s infill guide lists both cases; exemptions under the Site Alteration By-law can apply.
The Development Engineering Permit Application page (Town of Oakville, accessed November 9, 2026) says a site alteration permit is needed for pools, landscaping, patios and hardscaping, retaining walls, and all teardown rebuilds and additions (for work outside the building footprint), and that some work may be exempt under Schedule B of the Site Alteration By-law. Section 3 of the infill guide (Town of Oakville, August 2023, accessed November 9, 2026) adds that a grading and servicing plan may be required for building permits for teardown rebuilds where the footprint changes, and for all additions and new structures. Where the lot is under site plan control, that process applies first.
The guide recommends submitting the same grading design for the building permit and the DENG permit, and you may apply for the DENG permit first (section 4.3.3).
Town of Oakville grading plan requirements
The Town reviews residential grading plans against the Residential Infill Grading and Servicing Plan Checklist (Appendix A of the infill guide) and the Development Engineering Procedures and Guidelines. The main requirements are summarized below with the source for each; always check the current documents for your application.
Who prepares and seals the plan
Section 4.2 of the infill guide says the grading consultant must be an Ontario Land Surveyor or an engineer registered with Professional Engineers Ontario in civil or a relevant discipline. Checklist item 1.12 requires the plan to be stamped, signed and dated, with a statement that the designer reviewed the Town’s Stormwater Master Plan, is not affecting adjacent properties or Town infrastructure, and designed to Town standards.
For building permits, section 4.2 adds that the plan is prepared in accordance with Building Code 9.14.6.1.(1), as cited in the guide, so the building is located and the site graded without adversely affecting adjacent properties.
What the drawing must show
- One combined plan with all existing and proposed grading and servicing information, a full title block, a key plan, and a vector (not scanned) PDF at a minimum 1:200 metric scale (items 1.1 to 1.4).
- Property lines and right-of-way limits, abutting road features, existing driveways and any easements (items 1.5 to 1.7 and 1.10).
- Existing spot elevations at no more than 10 m intervals within the lot and at least 5 m beyond the property boundaries, including the floor and door sill elevations of the neighbouring houses (item 2.1).
- Proposed spot elevations at swale high and low points, tops and bottoms of slopes, grade changes, building corners and entrances (item 2.3).
- House siting elevations for rebuilds and additions: basement and garage slabs, finished floor, underside of footings and top of foundation wall (items 1.9 and 2.4).
- At least 0.15 m between the highest finished grade beside the house and the top of the foundation wall (item 2.29).
- Geodetic datum from Town of Oakville benchmarks, identified on the plan (item 2.24).
- A topographic survey completed no more than one year before submission, superimposed on the same drawing (item 2.25).
- Servicing for rebuilds: existing and proposed connections, inverts and pipe details (items 2.9, 2.35 and 2.36).
- Conservation Halton clearance where the property is within the Conservation Halton regulation limit or engineering floodline (item 1.13).
Source: Appendix A of the infill guide, pages 10 to 16 (Town of Oakville, accessed November 9, 2026).
Yard, swale and driveway slopes
Item 2.2 of the checklist asks for drainage arrows on all paved, granular and grassed areas with slopes between 2% and 5% for softscape and 1% to 5% for hardscape. Item 2.7 sets driveway slopes between 1% and 7%, and the driveway elevation at the property line must match the existing elevation.
Section 3.9 of the Development Engineering Procedures and Guidelines (Town of Oakville, Version 2.0, September 2023, accessed November 9, 2026) adds that all front and rear yard surfaces have a minimum 2.0% slope, rear yards have a maximum 5.0% grade for at least 5 m from the rear wall, and no yard surface is steeper than 3H:1V. Swales are at least 150 mm deep with 3H:1V side slopes and a minimum 2.0% slope (or 1% with a subdrain), for a maximum length of 60 m before the outlet.

Stormwater and on-site retention
Section 2.2 of the infill guide says new development must show that existing drainage patterns are maintained or improved, and how added runoff from larger roofs and hard surfaces is mitigated. Appendix C directs the designer to the Stormwater Master Plan maps: where the storm system next to the lot or downstream is shown orange or red (at or near capacity), mitigation such as infiltration or retention is required. Where no defined outlet exists for the lot, the same applies.
Item 2.5 says infiltration galleries without an overflow outlet are not approved ultimate outlets, and item 2.10 asks for a stormwater management report where applicable. Under section 3.9.2.1 of the manual, a dry well needs a report sealed by a professional engineer with a percolation test, a 48-hour drawdown and sizing for a 25 mm rainfall event, and it must be at least 5 m from buildings. For site plan developments, section 7.3.1 requires runoff from a 25 mm event to be retained on site.
Where the Town asks for runoff calculations, a separate stormwater management report may be part of the package.
Downspouts and sump pump discharge
Item 2.6 asks for downspout locations and flow direction on the plan. Section 3.7.8 of the manual says downspouts discharge to grade on concrete splash pads directed away from the building, typically to the front and rear yards rather than between houses, and must not be piped to a shared property line or aimed at a neighbour’s lot without a property line swale.
Item 2.11 asks for sump pump locations and discharge. The Town’s preferred approach is foundation drain discharge to grade on a splash pad about 1.5 m from the foundation, subject to the groundwater and drainage conditions in section 7.3.3 of the manual. Appendix C of the guide says sump pump discharge must not connect directly to the Town’s storm infrastructure.
Retaining walls
Item 2.3 requires top and bottom elevations on both sides of every proposed retaining wall. Walls near a lot line need a cross-section, must be at least 0.30 m inside the property, and their ends taper to no more than 0.15 m in height. Retaining walls that are not designated structures need a site alteration permit, and section 3.9.4 of the manual requires plans stamped by a professional engineer for walls over 1.0 m high.
Erosion and sediment control
Item 2.12 requires erosion and sediment control during construction to OPSS 805, with silt fence at the limit of construction and away from shared property lines (OPSD 219.130 heavy duty or 219.110 light duty). Items 2.21, 2.22 and 2.28 add catch basin sediment traps nearby, a mud mat at least 300 mm deep of 75 to 100 mm clear stone at the construction entrance, and a 0.30 m strip of sod or river rock with filter cloth along neighbouring properties. Our erosion and sediment control plan guide covers these measures in more detail.
Conservation Halton permission
Some Oakville lots are near a watercourse, valley, wetland, steep slope or the Lake Ontario shoreline and fall inside the area Conservation Halton regulates under Ontario Regulation 41/24. Conservation Halton’s Permitting page (accessed November 14, 2026) lists site grading and the placing, dumping or removal of any material among the development activities that need its permission in that area. Checklist item 1.13 of the Town’s infill guide asks for Conservation Halton clearance where the property is within the regulation limit or engineering floodline, so check the lot on Conservation Halton’s online regulation mapping before the plan is submitted.
Lot grading certification
The Town’s Lot Grading Certifications page (Town of Oakville, accessed November 14, 2026) says grading and stormwater device certifications are submitted when you request the final inspection for the security release. They are signed by an Ontario Land Surveyor or a Professional Engineer after an on-site inspection within 30 days before signing, using one of three templates: lot grading; lot grading and stormwater device; and stormwater device. The Development Engineering Permit Application page (accessed November 14, 2026) adds that the Town releases the permit security only after it has the lot grading certificate and an approved final inspection; that page also lists a Landscape Architect among the professionals who may sign.
Our grading certificate guide for Oakville explains this close-out step.
Oakville grading plan samples by Elmid
Three grading plans Elmid Design Inc. prepared for Oakville projects, shown as small thumbnails of the full sheets.



How the Oakville grading plan review works
For a DENG permit, the Town pre-screens the application, invoices the fee, reviews the plan, sets securities, issues the permit and closes it after a final inspection. For a building permit, a Development Engineering Technologist reviews the grading plan against the Building Code. Section 4.3 of the infill guide sets out both routes.
- Submit the Development Engineering Permit Application through the Town’s online portal, with the grading and servicing plan (section 4.3.1).
- The Development Permit Administrator pre-screens it against checklist Section 1 and, once complete, invoices the application fee.
- Engineering and forestry review comments are issued; the applicant revises and resubmits as needed.
- The applicant pays the securities and, for site alteration permits, the owner and applicant sign the Site Alteration Permit Agreement. The permit is then issued.
- After construction, the applicant requests a final inspection and submits the lot grading or stormwater device certificate. The Town inspects and releases the securities once any deficiencies are fixed.
Tree protection and removal are reviewed separately by the Town’s Forestry Department (section 4.3.3). No timeline or approval outcome can be promised; review time depends on the application and the comments raised.
Who does what on an Oakville grading plan?
An Ontario Land Surveyor prepares the boundary and topographic survey. The grading consultant, a P.Eng. or OLS, prepares and seals the grading and servicing plan and, after construction, visits the site and signs the lot grading certificate. Your contractor builds the work. The Town reviews, permits and inspects it.
Elmid Design Inc. is an engineering consultant. Within an agreed scope, a Professional Engineer at Elmid prepares and seals the site grading plan from your topographic survey and architectural drawings, with related stormwater and erosion and sediment control drawings where the Town asks for them. Where the Town requires a lot grading certificate, we visit the finished site and issue the certificate based on our own review. We do not prepare legal or topographic surveys, and we do not carry out excavation, grading or landscaping work.
If your project also needs a plot plan for the building permit, our article on site plan drawings for a building permit explains how it differs from a grading plan.
What to send Elmid for an Oakville grading plan
- Property address and a short description of the proposed work (rebuild, addition, pool, landscaping).
- Topographic survey (completed within the last year, or tell us if you do not have one yet).
- Architectural or landscape drawings, including house siting and floor elevations if available.
- Town correspondence: DEPA or building permit numbers and any review comments.
- Known drainage issues, with photos and their locations marked on a sketch.
Frequently asked questions
Do I need a grading plan for a pool in Oakville?
Usually, yes. The Town’s infill guide lists pools under the site alteration permit, which is supported by a grading and servicing plan. The guide includes a separate schematic pool permit grading plan, and the plan must show the pool location, elevations and a note that pool water is pumped to the front municipal boulevard.
Who can prepare a grading plan in Oakville?
The Town’s infill guide says the grading consultant must be an Ontario Land Surveyor or a Professional Engineer licensed by PEO in civil or a relevant discipline. The plan must be stamped, signed and dated, and include a statement that the designer reviewed the Stormwater Master Plan and is not affecting adjacent properties.
How old can the topographic survey be?
The Town’s checklist says the topographic survey must be completed no longer than one year before the grading plan is submitted. The survey information is placed on the same drawing as the proposed design, so a separate survey sheet is not needed. An Ontario Land Surveyor prepares the survey; Elmid works from it.
What slopes does Oakville require on a grading plan?
The infill checklist asks for drainage arrows with slopes between 2% and 5% on soft landscaping, 1% to 5% on hard surfaces and 1% to 7% on driveways. The Town’s engineering manual also sets a 2.0% minimum on yards, swales at least 150 mm deep and a maximum 3H:1V side slope.
Who signs the lot grading certificate after construction?
An Ontario Land Surveyor or a Professional Engineer signs it, after an on-site inspection within the 30 days before signing. The Town uses three templates: lot grading, lot grading and stormwater device, and stormwater device. The certificate and an approved final inspection are needed before the Town releases the permit security.
When does Oakville release the grading security?
The Town releases the permit security after it receives a lot grading certificate and approves a final inspection. The certificate is signed by a P.Eng. or an Ontario Land Surveyor who visited the finished site within the previous 30 days. Any deficiencies found at the Town’s inspection must be corrected before the security is released.
Do I need Conservation Halton permission for grading in Oakville?
Only if the lot is inside the area Conservation Halton regulates, such as land near a watercourse, valley, wetland, steep slope or the Lake Ontario shoreline. Its Permitting page lists site grading and the placing or removal of fill as development that needs its permission there. Check its online regulation mapping before you apply.
What should an Oakville grading plan quote include?
Compare quotes for the same work. Ask whether each quote includes a new topographic survey or assumes you already have one, which grading and drainage drawings it covers, and who handles Town comments and revisions. If final field review or certification applies, confirm whether it is included or priced separately. Budget separately for any applicable Town fees and permit security. Security, when required, is not a design fee; confirm the applicable release conditions with the Town.
Next step
If you need a grading plan for an Oakville rebuild, addition or pool, contact Elmid Design Inc. or call (647) 745-4507. Send your address, survey and drawings, and we will confirm the scope and prepare a proposal.
Sources
- Town of Oakville, Grading and Servicing Plan Guide for Residential Infill Developments (August 2023), sections 2 to 4 and Appendices A, C and D, accessed November 9, 2026.
- Town of Oakville, Development Engineering Procedures and Guidelines (Version 2.0, September 2023), sections 3.7.8, 3.9 and 7.3, accessed November 9, 2026.
- Town of Oakville, Development Engineering Permit Application Process, section “Lot grading certification and security releases”, accessed November 14, 2026.
- Town of Oakville, Property Drainage and Grading, accessed November 9, 2026.
- Town of Oakville, Lot Grading Certifications, accessed November 14, 2026.
- Conservation Halton, Permitting (Ontario Regulation 41/24), accessed November 14, 2026.
This article is general information, not advice for a specific property. Town requirements change; confirm the current guide, checklist and by-laws with the Town of Oakville before you apply.