Site Servicing Plan in Durham Region: Regional vs Municipal Approvals

A site servicing plan in Durham Region goes to two levels of government. The Regional Municipality of Durham owns the watermains and sanitary sewers and reviews the water and sanitary connections, work on Regional roads and anything built to its design specifications. The local municipality (Ajax, Brock, Clarington, Oshawa, Pickering, Scugog, Uxbridge or Whitby) reviews storm drainage, lot grading, local roads and the site plan itself. The plan has to satisfy both.

Illustrative site servicing plan of a residential lot in plan view: three separate service lines run from the house to three separate mains in the road, blue water to the watermain, green sanitary to the sanitary sewer and orange storm to the storm sewer, each with an inspection point inside the property line

The image at the top of this page is illustrative only: it shows three separate service connections, water, sanitary and storm, each running to its own main in the road. It is not a project drawing and shows no design values.

This guide is for homeowners, builders and architects with a project in Durham Region: what the plan shows, which office reviews which part, and who prepares what.

Elmid Design Inc. is an engineering consultant. We prepare the servicing and grading design. A contractor you hire installs the pipes, and the Region and the municipality make the approval decisions.

On this page

What is a site servicing plan?

A site servicing plan is an engineering drawing that shows how a property connects to water, sanitary sewer and storm drainage. It locates each pipe, its size and material, its slope and the elevation where it crosses the property line, and it shows how the new pipes meet the mains in the street.

The City of Oshawa gives a useful list of what a servicing plan must indicate:

  • the size, length, location, grade, material and bedding of proposed storm sewers, sanitary sewers and water connections;
  • existing and proposed stormwater systems and natural drainage within 30 m of each lot boundary;
  • utilities, structures, roads and paving within 30 m of each lot boundary;
  • service inverts at the property line.

Other Durham municipalities word their checklists differently; use the current one for your municipality.

Why does a Durham site servicing plan go to two levels of government?

Because Durham has a two-tier structure in which the Region owns the water and wastewater system and the local municipalities own most storm drainage and local streets. Each level reviews the part of the plan that connects to its own infrastructure.

Oshawa sets out the split plainly in its Subdivision Development Engineering Process Guide (last updated March 2026). The Region is responsible for all sanitary sewers and watermains, with their appurtenances, on road allowances and registered easements. The Region also manages the Regional roads and most storm sewers within them. The City is primarily responsible for storm water drainage and City streets.

The planning side changed on January 1, 2025. Under Bill 23, the province now defines Durham as an “upper-tier municipality without planning responsibilities”. The Region says its eight area municipalities have assumed approval authority for all Planning Act decisions, except as prescribed by the province. Site plan approval therefore rests with the local municipality.

The Region still takes part: its Development Advisory Services section co-ordinates Regional comments on local development applications, and the municipality decides.

What does the Region review, and what does the local municipality review?

In short: the Region reviews what connects to its pipes and roads, and the municipality reviews the site, its grades and its storm drainage. The table sums up the usual split. Specific responsibilities vary by municipality and by project, so confirm them with the municipality before design starts.

Part of the planRegion of DurhamLocal municipality
Water serviceOwns the watermain; water connections built to its design specifications and standard drawingsVaries; confirm with the municipality
Sanitary serviceOwns the sanitary sewer; sanitary connections built to its specifications and Sewer Use By-lawVaries; confirm with the municipality
Storm drainageMost storm sewers within Regional roadsStorm drainage, storm connections to City or Town sewers, stormwater management
GradingDrainage onto a Regional road allowanceLot grading, site alteration and grading permits
Roads and accessEntranceway and Road Occupancy Permits on Regional roadsLocal road access and work in local road allowances
Site plan decisionComments on the applicationDecides site plan approval

What does the Region check on water and sanitary connections?

The Region checks that new water and sanitary connections meet its Design and Construction Specifications for Regional Services and its standard drawings. The Region says these are to be used and followed by consultants and contractors for the design and construction of Durham Region road, water and sanitary sewer infrastructure.

The design specifications are published as separate chapters: Engineering Submissions, Roads and Entranceways, Storm Sewers, Sanitary Sewers, Watermains, Service Connections, and Traffic Control Devices, Pavement Markings, Signage and Roadside Protection. The S-100 standard drawings cover storm and sanitary sewer details. Check the current edition before design.

The Service Connections chapter (dated May 2018) sets several rules that shape a plan:

  • Individual services: sanitary and water service connections for single and semi-detached houses, link dwellings and duplexes are individual connections.
  • No clean water in the sanitary: foundation drains (weepers) and roof leaders may not connect to the sanitary sewer, as per the Regional Sewer Use By-law.
  • Water service location: on a single-family lot, the water service is installed at the mid-point of the frontage, to the right of the sanitary connection, ending at least 0.15 m inside the property line.
  • Backflow plans: proposed commercial, industrial, institutional and multi-residential developments give the Region, for approval, a plan showing the backflow preventer size, type and location.
  • Rear-yard connections: connections to the rear of a building need a Region rear-yard sewer agreement, and the Region does not maintain them on private property.

For a house on a street where Regional services need to be installed at the property line, the Region has a Connection Permits process. The owner completes the Region’s form and the Works Department makes contact about connecting the home to the sewer or water system. The Region notes that frontage fees and connection charges may apply, listed in its Fees and Charges Schedule.

When do Regional roads affect the servicing plan?

Regional roads matter whenever a driveway, a service trench or surface drainage reaches a Regional road allowance. The Region issues its own permits there, and it does not issue permits for work within local municipal road allowances.

Entranceway permits. Under By-law 2024-028, a permit is needed before building a new entranceway or changing an existing one within a Regional road allowance. Proposed entranceways are designed to the Region’s Design Specifications for Roads, Structures and Entranceways and the current Ontario Provincial Standard Drawings (OPSD). If the property also borders a local road, the Region will require the entranceway to connect to the local road where possible.

Entranceways for commercial, industrial and multi-unit residential sites are typically approved through the municipal Site Plan Approval process, and a separate entranceway permit is not required for an entranceway that is part of an approved site plan.

Road Occupancy Permits. Any works within the Regional right-of-way need a separate Road Occupancy Permit, which allows a contractor to work there. The servicing plan shows where the trench and restoration will be.

Drainage. The Region asks that entranceways be designed so surface water from the entranceway or the adjoining property does not discharge onto the Regional right-of-way. The grading plan has to show where that water goes instead.

What does the local municipality review?

The local municipality reviews the site itself: grading, storm drainage, stormwater management, local road connections and the site plan. It also issues the building permit, which is separate from the servicing review.

Grading and site alteration. Oshawa’s Site Alteration By-law applies to all land in the City and regulates activities such as removing or adding soil that change land levels. Its grading plan requirements include existing and proposed grades with surface flow directions, topography extending at least 30 m beyond each lot boundary, overland flow routes and roof-water leader outfalls.

Storm connections. Oshawa’s building permit page tells applicants to contact the City’s Engineering Services if any part of the project requires a storm sewer connection. Its Engineering Design Criteria Manual (November 2024) sets out site servicing and grading plan requirements and the rules for site plan storm sewer connections.

Infill permits. Some municipalities have a separate engineering permit for infill lots. In Whitby, for example, a Grading, Servicing and Drainage Permit is typically required before applying for a building permit on an infill lot.

Site plan approval. Where site plan control applies, the municipality decides the application. Ask early whether it applies, because the answer changes the drawing package.

What does a Durham site servicing plan show?

A Durham site servicing plan shows every pipe between the building and the mains, with enough levels and details for both the Region and the municipality to check their parts. A typical sheet includes:

  • Base information: property lines, easements, existing buildings, existing services and the street, from a current survey.
  • Water service: size, material and route from the watermain to the building, the curb stop location, and for larger sites any fire service, hydrants and backflow preventer.
  • Sanitary service: size, slope and route to the sanitary main, with invert elevations at the building, at the property line and at the main, and any cleanouts or maintenance holes.
  • Storm service: roof leaders, foundation drain discharge and the storm service connection to the storm sewer main, or an approved surface outlet, kept separate from the sanitary.
  • Crossings: where services cross each other or other utilities, with separations shown.
  • Road works and notes: the trench and restoration in the road allowance, identified as Regional or local, with references to the applicable standard drawings.

Larger sites add calculations, such as sanitary flows and storm sewer design; Oshawa asks for storm sewer design calculations for proposals of 0.4 hectares or greater.

How is servicing different on rural lots in Durham?

Where a rural property is not on municipal water or sewer, “servicing” usually means a private well and a septic system rather than connections to Regional mains. Whether a particular lot can connect is a question for the Region and the municipality.

Durham Region Health Department is responsible for approving the design and building of private sewage systems in the Region, under the Ontario Building Code. Its septic application asks for a site plan, because the inspector needs to know where all parts of the system and the well are on the property.

Grading and drainage on a rural lot still matter to the municipality, and access to a Regional road still needs a Regional entranceway permit.

Where can you read about site servicing in each Durham municipality?

Each Durham municipality has its own standards, forms and review staff. Elmid has a guide for each one:

Who does what on a Durham servicing project?

Several people contribute, and each has a defined role. The engineer designs the servicing, the surveyor provides the base information, the contractor builds, and the Region and the municipality review and approve.

  • Ontario Land Surveyor: prepares the topographic survey and confirms legal property lines and easements. Legal surveying is separate from the engineering design.
  • Architect or designer: designs the building and usually prepares the architectural site plan, which the servicing plan must match.
  • Geotechnical engineer: where needed, reports on soils and groundwater.
  • Engineering consultant (Elmid): prepares the site servicing plan, grading plan, details and calculations within an agreed scope, coordinates with the Region’s specifications and the municipality’s standards, and responds to review comments on the engineering.
  • Contractor: obtains construction-stage permits such as a Regional Road Occupancy Permit, and installs the services.
  • Region of Durham: reviews connections to its water, sanitary and Regional road systems and comments on development applications.
  • Local municipality: reviews grading, storm drainage and the site plan, and issues the building permit.

Elmid is not a contractor and does not install, excavate or connect services.

What should you send Elmid to start a Durham servicing plan?

Send the property address and municipality, a current survey, the architectural site plan or concept, and any comments already received from the municipality or the Region. With these, Elmid can confirm the scope and prepare a written proposal.

  • Survey: a current topographic survey with property lines, easements, existing buildings and grades.
  • Design drawings: the architect’s or designer’s site plan and floor plans, or a concept sketch.
  • Existing services: any information on where the existing water and sewer services enter the building, and photos of the street frontage.
  • Municipal and Regional records: pre-consultation notes, review comments or service records, if you have them.

Please email drawings and photos after first contact, because our contact form does not take attachments.

Frequently asked questions

Does the Region of Durham approve site plans?

No. Since January 1, 2025, the Region of Durham is an upper-tier municipality without planning responsibilities, and its eight area municipalities have assumed approval authority for Planning Act decisions, except as prescribed by the province. The Region still comments on local development applications as the owner of the water, sanitary and Regional road systems.

Who reviews storm drainage on a Durham site servicing plan?

Usually the local municipality. Oshawa, for example, says it is primarily responsible for storm water drainage and City streets. Within Regional roads, however, most storm sewers belong to the Region, so a storm connection or outlet near a Regional road should be confirmed with both.

Can foundation drains connect to the sanitary sewer in Durham Region?

No. The Region’s Service Connections design specification states that foundation drains (weepers) and roof leaders are not permitted to connect into the sanitary sewer system, as per the Regional Sewer Use By-law. The servicing plan routes them to the storm system or an approved surface outlet.

Do I need a Regional permit for a driveway on a Regional road?

Usually yes. Under By-law 2024-028, the Region requires an entranceway permit before a new or changed entranceway within a Regional road allowance. Entranceways for commercial, industrial and multi-unit residential sites are typically approved through the municipal site plan process instead, and any work in the right-of-way needs a separate Road Occupancy Permit.

Does Elmid install water and sewer services?

No. Elmid Design Inc. is an engineering consultant, not a contractor. We prepare site servicing plans, grading plans and related reports within an agreed scope. A contractor you hire installs the services, and the Region and the municipality review and approve the work.

How much does a site servicing plan in Durham Region cost?

Costs depend on the site and scope: the size of the project, whether it is a single lot or a larger site, and which drawings and reports the Region and the municipality require. Elmid prepares a written proposal after reviewing your survey and drawings, and offers a free consultation and a free quote.

Areas we serve

Elmid Design Inc. prepares site servicing plans and grading plans across Durham Region, including Ajax, Brock, Clarington, Oshawa, Pickering, Scugog, Uxbridge and Whitby, and in Toronto and the rest of the Greater Toronto Area, including York, Peel and Halton regions. We also work in other Ontario municipalities, depending on project scope and availability. Contact us to discuss your project.

Related articles

Sources

This article is general information, not advice for a specific property. Requirements change over time; confirm current requirements with the Region of Durham and your local municipality before you apply.

Share This Guide

Related Engineering Guides

Contact Elmid Design Inc.

Let’s discuss
your project.

Engineering design services across Toronto, the GTA and Ontario.

Contact Elmid Design Inc. for engineering and design support. Tell us about your property and proposed work so we can help identify the next steps.

Contact Us graphic with email and phone symbols over an engineering site plan.

Supporting projects in Toronto and other communities across the GTA and Ontario.

A CLEAR FIRST STEP

Contact Our Engineering Team

Share what you have now. You don’t need a complete drawing package to start.

Scroll to Top
Planning a project? Speak with our engineering team. ☎ (647) 745-4507✉ info@elmid.ca Request a Proposal →